To align two linear guide rails correctly, establish one rail as the master or reference rail, secure it to a properly prepared machine datum, then align the second rail parallel to the master rail before fully tightening its mounting bolts. The secondary rail can be aligned with a straightedge and dial indicator, the moving table, a dedicated alignment jig, or another manufacturer-approved method.
The most important principle is:
Do not try to align both rails independently. Establish one accurate reference rail first, then align the second rail from it.
Two rails that are individually straight but not parallel to each other can force the carriages into conflicting paths. That can create increased running resistance, internal loading, binding, premature wear, and poor machine accuracy.
Why Two Linear Guide Rails Must Be Aligned
A two-rail linear guide system works as one mechanical structure.
The rails support the same moving table, carriage plate, gantry, or machine axis.
If the rails are not aligned relative to each other, the carriages may be forced sideways or vertically as the table moves.
Possible consequences include:
increased rolling resistance
tight spots
carriage binding
excessive internal loading
uneven load distribution
increased wear
shorter service life
reduced positioning repeatability
poor machine accuracy
increased noise
The goal is not simply to make both rails look straight.
The goal is to make them geometrically compatible with the same motion path.
Start With the Machine Base
Before aligning the rails, inspect the mounting surfaces.
Look for:
chips
burrs
raised material around mounting holes
dents
corrosion
damaged datum shoulders
contamination
uneven seating surfaces
THK's installation guidance specifically calls for removing burrs, dents, dust, and other contamination from the machine mounting surface before installing the guide rails.
A precision alignment procedure cannot compensate for a chip trapped beneath a rail.
Do Not Use Rail Alignment to Correct a Bad Base
The machine structure should provide the geometry that supports the guide system.
The rails should not be forced into alignment against:
warped mounting surfaces
badly machined shoulders
excessive height variation
major hole-location errors
structural distortion
If the base geometry is outside the requirements of the machine design, correct the structure before attempting final rail alignment.
Otherwise, tightening the rails may simply lock distortion into the guide system.
Step 1: Identify the Master Rail
In a two-rail system, one rail should be established as the primary reference.
This is commonly called the:
master rail
The other rail becomes the:
secondary rail
or:
subsidiary rail
THK specifically identifies master rails in certain matched LM Guide arrangements and uses the master rail as the positioning reference for the guide system.
The alignment sequence is therefore:
machine datum → master rail → secondary rail → carriages → moving table
Step 2: Identify the Reference Surface
If the machine has a machined shoulder or side datum, determine which side of the master rail is intended to contact it.
Manufacturers may mark rail reference surfaces differently.
THK, for example, identifies the rail reference surface with a line marking on applicable LM Guide systems.
Check the documentation for the actual rail family rather than assuming either side can be used interchangeably.
Step 3: Position the Master Rail
Place the master rail on the prepared mounting surface.
Install the rail mounting bolts lightly at first.
Do not fully torque every bolt immediately.
The rail needs enough freedom to:
seat on the base
contact the reference shoulder
establish straightness
accommodate the intended tightening sequence
THK's mounting procedures begin with temporary fastening before the rail is fully seated and secured.
Step 4: Seat the Master Rail Against the Datum
If a side reference surface is available, press the rail consistently against it.
Depending on the machine design, this may be accomplished with:
set screws
side clamps
a temporary clamp
rail pressers
another controlled fixture
THK describes a method in which the rail is temporarily fastened and then pressed against the side reference surface at each mounting location before the bolts are fully tightened.
The objective is to establish consistent rail-to-datum contact without bending the rail into an incorrect shape.
Step 5: Tighten the Master Rail Progressively
Once the master rail is seated correctly, tighten the mounting bolts according to the manufacturer's recommended sequence and torque.
Do not randomly tighten bolts.
Depending on the specific mounting arrangement, manufacturer procedures may call for progressive tightening:
from one end toward the other
from the center toward the ends
The correct method depends on the guide family and installation arrangement.
For one THK master-rail mounting method without set screws, the rail is pressed to the side datum and bolts are fully fastened progressively from one rail end to the other.
The important lesson is:
follow the tightening sequence specified for the actual installation method rather than assuming one universal sequence.
Step 6: Verify the Master Rail
The secondary rail can only be aligned correctly if the master rail is correct first.
Depending on machine accuracy requirements, verify:
straightness
seating against the datum
height
orientation
running indication
Possible measuring tools include:dial indicator
test indicator
precision straightedge
precision level
height gauge
laser measurement equipment for demanding applications
The required measurement method depends on the machine design and tolerance.
Step 7: Place the Secondary Rail
Install the second rail on its mounting surface.
Insert the mounting bolts but leave them sufficiently loose to permit adjustment.
Do not fully tighten the secondary rail before checking its relationship to the master rail.
THK's guidance specifically treats the subsidiary rail as the rail that must be mounted parallel to the already correctly installed master rail.
What Does “Parallel” Mean for Linear Rails?
Parallelism is not limited to one dimension.
Two rails may need to be aligned in:
lateral position
vertical height
straightness
angular relationship
A secondary rail can be horizontally parallel but vertically incorrect.
For some installations, both side-to-side and height relationships must therefore be checked.
THK documentation for parallel JR rails specifically describes using a dial gauge to check the side face and top face of the second rail while mounting it, allowing parallelism and level to be adjusted together.
Method 1: Align the Second Rail With a Straightedge and Dial Indicator
THK recommends a straightedge method for aligning a subsidiary rail parallel to the correctly installed master rail.
The basic process is:
Establish the master rail.
Position a precision straightedge relative to the master rail.
Use a dial indicator to make the straightedge parallel with the master-rail reference.
Position the indicator against the secondary rail.
Adjust the secondary rail progressively.
Tighten mounting bolts as straightness is confirmed.
THK describes placing a straightedge between the rails, aligning it parallel to the master rail with a dial gauge, and then fastening the subsidiary rail progressively while checking its straightness.
This method is useful when the rails are accessible and a reliable measurement reference can be established.
Method 2: Align the Secondary Rail Using the Moving Table
Another manufacturer-documented approach uses the table or a temporary measurement plate to establish the relationship between rails.
The general idea is:
Secure the blocks on the master rail to the table.
Temporarily fasten the secondary rail and its block.
Mount a dial indicator on the table.
Position the indicator against the side of the secondary block or rail.
Move the table along the axis.
Adjust the secondary rail progressively.
Tighten the rail bolts as parallelism is confirmed.
THK documents this approach as using the parallelism of the table.
Because the table rides on the correctly installed master rail, it provides a moving reference from which the secondary rail can be checked.
Method 3: Let the Secondary Rail Follow the Master Rail
Certain installations can use the table and carriages themselves to help establish the secondary rail.
THK documents a procedure in which:
the blocks on the master rail are fully secured
one block on the secondary rail is secured
another secondary block remains temporarily fastened
the subsidiary rail bolts are progressively tightened
This allows the secondary side to establish its position relative to the master rail through the assembled structure.
This method should follow the manufacturer's procedure carefully.
Do not simply bolt everything together tightly and assume the carriages will force the rails into proper alignment.
Method 4: Use an Alignment Jig
A dedicated alignment jig can establish the required relationship between the master and secondary rail.
THK documents a jig method in which a fixture references the master side and is used to establish the subsidiary rail position at successive mounting-hole locations.
A good jig can be useful for:
production machinery
repeated builds
long rails
installations where consistent spacing must be duplicated
The jig itself must be sufficiently accurate for the machine's requirements.
Method 5: Measure Both Side and Height Alignment
Some guide systems require simultaneous control of:
side-to-side parallelism
vertical level
For THK's JR guide example, one rail is fixed first and a dial gauge mounted on a block is used to measure both the side face and top face of the other rail during mounting.
This approach illustrates an important concept:
Two rails should be considered in three-dimensional space, not just from a top view.
Why Rail Spacing Alone Does Not Prove Alignment
Suppose two rails are designed to be:
500 mm apart
Measuring 500 mm between them at one point does not prove they are parallel.
For example:
one end could measure 500 mm
the opposite end could measure 500.5 mm
The average spacing may look correct, but the rails are converging or diverging.
Likewise, the rails could have the correct lateral spacing while one rail rises vertically relative to the other.
Alignment should therefore be checked along the rail length.
Measure at Multiple Positions
Do not verify parallelism at only one point.
Check the secondary rail at:
beginning of travel
intermediate positions
opposite end
additional locations for long rails
The spacing and indicator reading should remain within the tolerance required by the guide system and machine.
Long rails deserve particular attention because small angular errors accumulate over distance.
Example: Small Angular Error Over a Long Rail
Suppose the second rail is laterally displaced by only:
0.20 mm
from one end to the other across a:
2,000 mm
rail.
That may appear small when looking at the overall machine.
But the carriages are precision elements, and the table attempts to maintain a fixed relationship between them.
The correct question is not whether the rail “looks straight.”
It is whether the measured parallelism satisfies the allowable installation tolerance for:
the specific guide
preload class
rail arrangement
machine accuracy requirement
Do Not Invent a Universal Parallelism Tolerance
There is no single parallelism tolerance that should be applied to every two-rail linear guide installation.
Allowable installation error can depend on:
manufacturer
guide family
guide size
accuracy class
preload
block spacing
rail spacing
machine rigidity
application
Use the manufacturer's technical data for the exact guide.
Avoid rules such as:
“all linear rails should be aligned within X mm”
unless that value is confirmed for the selected guide system.
Preload Makes Alignment More Important
A more heavily preloaded guide generally has less internal clearance available to accommodate mounting error.
That can make installation geometry particularly important.
However, preload should not be used as a shortcut for describing allowable misalignment.
The exact relationship is product-specific.
The practical rule is:
the more demanding the guide system, the less you should rely on the carriage to absorb installation error.
Why You Should Not Force the Second Rail Into Position
A common mistake is tightening the table onto all carriages and letting the bolts forcibly pull the secondary rail into place.
This can create hidden internal loading.
The guide may move after assembly, but the blocks may already be fighting:
lateral misalignment
vertical mismatch
table distortion
rail twist
A system that moves is not necessarily a correctly aligned system.
Smooth Motion Is a Check, Not the Entire Alignment Procedure
After installation, manually move the table through the full usable stroke.
Look for:
uniform resistance
tight spots
roughness
noise
visible movement of the rail
changes in running force
Smooth travel is important, but it is not sufficient proof of precision alignment.
A lightly preloaded guide may tolerate some error and still feel acceptable by hand.
Precision equipment should also be checked with suitable measurement instruments.
Use a Dial Indicator to Check Relative Motion
A dial or test indicator is one of the most useful tools for rail alignment.
Depending on the alignment method, the indicator can be referenced to:
the master rail
a straightedge
the moving table
the machine datum
The indicator can then sweep the secondary rail to reveal changes in relative position.
This gives measurable information rather than relying on visual judgment.
Horizontal and Vertical Parallelism
Two rails can have error in at least two important planes.
Horizontal Parallelism
This is the side-to-side relationship between the rails.
Excessive error can cause lateral forcing of the blocks.
Vertical Parallelism
This is the height relationship between the two rail paths.
Excessive vertical difference can twist or distort the moving table.
The machine design determines how much error can be tolerated.
The Table Can Magnify Alignment Problems
A rigid table connects the carriages together.
If the rails are misaligned, the table may force the carriages to conform to its geometry.
That can create a closed structural loop:
master rail → block → table → second block → secondary rail → machine base
Any geometric disagreement inside that loop can produce internal forces.
This is why:
machine base accuracy, rail alignment, and table geometry must work together.
Rail Parallelism Is Different From Rail Straightness
Straightness describes the geometry of an individual rail path.
Parallelism describes the relationship between two rail paths.
You can have:
two straight rails that are not parallel
two parallel rails that both follow an unwanted curve
A high-quality installation must consider both.
Rail Alignment Is Different From Rail Spacing
Rail spacing is the designed distance separating the rails.
Alignment determines whether that spacing is maintained correctly along the guideway.
For example, the design may specify:
S = 500 mm
The rails need to maintain the intended relationship along their entire working length rather than simply being 500 mm apart at one location.
Rail Alignment Is Different From Block Spacing
Block spacing is the longitudinal distance between carriages on the same rail or axis.
It affects the support footprint and moment reactions.
Rail alignment concerns the geometric relationship between the guide paths.
Both matter, but they solve different problems.
What If the Machine Has Two Precision Datum Shoulders?
Some machine bases are designed with accurately machined reference shoulders for both rails.
This can simplify installation if those datums were manufactured to the required:
straightness
spacing
parallelism
In that case, both rails may be seated against their respective references according to the machine and guide manufacturer's installation procedure.
However, the datums themselves should still be verified.
Two shoulders do not automatically guarantee correct rail alignment merely because they exist.
What If the Secondary Rail Has No Datum Shoulder?
This is common.
The master rail may have a precision side reference while the secondary rail floats laterally during alignment.
In this arrangement:
mount the master rail accurately
place the secondary rail
measure its relationship to the master
adjust progressively
tighten its mounting bolts as alignment is established
This configuration gives the installer direct control over rail parallelism.
When the Moving Table Is Used as the Alignment Reference
Using the table can be efficient when:
the master rail is already correct
the table is sufficiently rigid and accurate
block mounting surfaces are properly machined
the manufacturer supports the method
But the table itself must not contain major geometric error.
If the table mounting surfaces are twisted, using it blindly as an alignment fixture can transfer that error into the rail system.
Use Temporary Tightening During Alignment
The secondary rail mounting bolts should generally remain only temporarily fastened while adjustments are being made.
This allows the rail to move slightly as parallelism is established.
After the rail has been measured and positioned correctly, tighten the bolts progressively according to the applicable procedure.
Fully tightening everything before alignment is complete removes the ability to make controlled adjustments.
Tighten Bolts Progressively
Once the secondary rail is aligned, tighten its fasteners in a controlled sequence rather than randomly jumping between mounting holes.
THK's documented alignment methods describe progressively fastening the subsidiary rail as straightness or parallelism is established along the axis.
The specific sequence should match the chosen alignment method.
Use the Correct Bolt Torque
Final bolt torque should follow the manufacturer recommendation for:
guide series
fastener size
bolt grade
machine-base material
specified thread condition
Excessive torque can damage threaded holes or distort components.
Insufficient torque can allow rail movement.
Alignment work is not complete until the rail is securely fastened under the intended mounting conditions.
Check Alignment Again After Final Torque
Final tightening can sometimes produce small positional changes.
After the secondary rail has been torqued:
sweep the rail again
verify horizontal parallelism
verify vertical relationship if required
move the table through its complete travel
investigate any changed readings or tight spots
Do not assume that a temporarily aligned rail remains identical after full clamping force is applied.
Verify the Complete Stroke
Check alignment across the complete working range.
A rail can appear acceptable near one end and become increasingly misaligned farther along the axis.
This is especially relevant for:
long stroke systems
large gantries
rails mounted on fabricated structures
machines assembled from multiple base sections
The longer the guideway, the more important it becomes to verify geometry at multiple locations.
Long Rails Require More Care
Long rails magnify small errors.
They may also be more sensitive to:
base straightness
thermal conditions
handling
joint alignment
mounting-hole accumulation
For very long guideways, the selected guide family may also require jointed rails.
If jointed rails are used, the individual rail sections and joints must be aligned as part of the overall guideway.
Aligning Jointed Rails
Jointed rails introduce another alignment location: the rail joint.
The transition must allow the carriage to pass smoothly without an undesirable step or offset.
THK documentation for model JR shows the use of:
joint fittings
dial gauges
adjustment screws
to align rail sections laterally and vertically at the joint.
For factory-supplied matched or jointed rails, preserve:section sequence
orientation
match markings
THK also notes that jointed rails supplied for parallel arrangements may be manufactured so the guideways are aligned as intended, and joint match marks should be maintained during installation.
Check Matched Rail Identification
Some precision guide systems are supplied as matched sets.
THK states that LM rails mounted on the same plane may carry the same serial number and identifies the master rail with a specific marking for applicable precision arrangements.
If rails and blocks are marked as matched components:
do not mix their positions casually.
Record:
rail identification
block identification
orientation
before disassembly.
Common Two-Rail Alignment Mistakes
Aligning Both Rails Independently
Establish a master rail first and align the second rail relative to it.
Checking Rail Spacing at Only One Point
Correct spacing at one location does not prove parallelism over the full stroke.
Checking Only Side-to-Side Alignment
Vertical height differences can also create problems.
Using the Carriages to Force the Rails Into Position
This can introduce internal loading rather than correcting the geometry.
Fully Tightening the Secondary Rail Too Early
Leave adjustment capability until parallelism is established.
Ignoring the Machine Base
A precision rail cannot correct major base errors.
Guessing at Acceptable Parallelism
Use manufacturer data for the actual guide.
Ignoring Tight Spots
A change in resistance during travel can indicate geometric problems.
Assuming Smooth Travel Means Perfect Alignment
Smooth motion is useful feedback but not a complete precision measurement.
Mixing Matched Components
Preserve manufacturer-specified matched rail and block relationships.
A Practical Two-Rail Alignment Procedure
For a typical precision two-rail installation:
Step 1: Prepare the Base
Clean and inspect both rail mounting surfaces.
Step 2: Identify the Master Rail
Confirm the correct reference side and rail orientation.
Step 3: Temporarily Install the Master Rail
Leave fasteners sufficiently loose for seating.
Step 4: Seat the Master Rail Against Its Datum
Use the machine reference shoulder or an approved alignment reference.
Step 5: Secure and Verify the Master Rail
Tighten progressively and measure its installed geometry.
Step 6: Temporarily Position the Second Rail
Do not fully tighten it.
Step 7: Choose the Alignment Method
Use:
straightedge and indicator
moving table
following method
alignment jig
or another approved procedure.
Step 8: Check Side-to-Side Parallelism
Measure at multiple locations.
Step 9: Check Vertical Relationship
Verify rail height or top-face relationship where required.
Step 10: Tighten the Secondary Rail Progressively
Secure the rail as alignment is confirmed.
Step 11: Recheck After Final Torque
Verify that tightening did not shift the rail.
Step 12: Install or Finalize the Table
Avoid forcing the carriages into position with the table bolts.
Step 13: Check Full-Stroke Motion
Move the axis slowly through its complete usable travel.
Step 14: Measure Final Machine Geometry
For precision machinery, verify running straightness, parallelism, and other required machine tolerances.
How to Troubleshoot a Tight Spot
If the table becomes harder to move at one point:
Note the exact position.
Check secondary rail parallelism at that location.
Check rail height.
Inspect for debris beneath the rail.
Check mounting bolt sequence and torque.
Inspect carriage condition.
Verify the machine base.
Check whether the table itself is twisting the guide system.
Do not simply loosen random rail bolts until the axis moves freely.
Use the tight spot as diagnostic information.
What If the Rails Cannot Be Brought Into Alignment?
If acceptable alignment cannot be achieved, investigate the underlying geometry.
Possible causes include:
incorrect base machining
incorrect rail spacing
mounting holes pulling the rail sideways
warped machine frame
rail damage
incorrect rail or carriage
table distortion
improperly matched components
jointed rail sections installed in the wrong order
The correct solution may require correcting the machine structure rather than continuing to adjust the rails.
Linear Automation USA's Perspective
At Linear Automation USA, we treat two-rail alignment as a system geometry problem rather than simply a rail-installation problem.
The rails, carriages, machine base, and moving table create one structural loop.
If those components disagree geometrically, the guide blocks can be forced to absorb the error.
For a two-rail installation, we recommend confirming:
exact manufacturer
rail series
rail size
master/reference rail
reference surface
rail spacing
block spacing
machine datum geometry
mounting-hole pattern
required installed accuracy
preload or clearance class
bolt size and torque
lubrication requirements
Our rule is:
Establish one accurate rail first. Measure the second rail relative to it. Do not use the carriages to hide alignment errors.
Linear Automation USA supplies industrial profile rail systems from SBC Linear, WON Linear, Schaeffler, and other supported product families.
For alignment questions involving a new or replacement guide system, contact Linear Automation USA.
Two-Rail Alignment Checklist
Before alignment:
Verify rail manufacturer and series.
Confirm rail and block orientation.
Identify the master rail.
Identify the reference surfaces.
Inspect the machine base.
Remove burrs and contamination.
Verify rail spacing and mounting-hole locations.
Master rail:Temporarily install the rail.
Seat it against the datum.
Tighten progressively.
Use the correct bolt torque.
Verify straightness and height.
Secondary rail:Temporarily fasten the rail.
Choose the alignment method.
Check lateral parallelism.
Check vertical relationship.
Measure at multiple points.
Tighten progressively.
Recheck after final torque.
Final assembly:Install or finalize the moving table.
Avoid forcing block alignment with bolts.
Move the axis through its complete stroke.
Investigate tight spots.
Verify final machine accuracy where required.
Frequently Asked Questions
How Do You Align Two Linear Guide Rails?
Install one rail accurately as the master rail, then align the second rail parallel to it using a dial indicator, straightedge, moving table, alignment jig, or another manufacturer-approved method.
Which Rail Should Be Aligned First?
The master or reference rail should be established first.
How Do You Check Linear Rail Parallelism?
A dial indicator can be referenced from the master rail, a precision straightedge, or the moving table and swept along the secondary rail to measure changes in relative position.
Should You Check Rail Height Too?
Yes when the machine requires it. Two rails can be horizontally parallel but vertically misaligned.
Can the Moving Table Be Used to Align the Second Rail?
Yes. THK documents methods that use the table or temporary measurement table to establish subsidiary-rail parallelism relative to the master rail.
Can the Secondary Rail Follow the Master Rail?
Certain guide installation procedures allow the table and carriage arrangement to help establish the secondary rail position. Follow the manufacturer's documented procedure rather than forcing the system together.
What Is the Acceptable Parallelism Tolerance?
There is no single universal value. Use the tolerance specified for the actual guide family, size, preload, accuracy class, and machine requirements.
Should Both Rails Be Fully Tightened Before Installing the Table?
The master rail should normally be established first, while the secondary rail remains adjustable until its alignment relative to the master has been confirmed.
What Causes Linear Guide Binding?
Possible causes include rail parallelism error, height mismatch, poor base geometry, contamination, carriage damage, table distortion, or excessive internal loading.
Can Misaligned Rails Reduce Linear Guide Life?
Misalignment can create additional carriage loading and uneven running conditions, which can contribute to accelerated wear and reduced system performance.
Does Smooth Motion Mean the Rails Are Properly Aligned?
Not necessarily. Smooth travel is an important check, but precision systems should also be measured against the applicable installation tolerance.
Should I Measure Parallelism Along the Entire Rail?
Yes. Check multiple positions across the complete usable stroke, particularly on long guideways.
Need Help Aligning a Two-Rail Linear Guide System?
For a new installation, provide:
manufacturer
rail series
rail size
rail length
rail spacing
number of carriages
block spacing
machine mounting arrangement
reference shoulder configuration
accuracy requirements
preload or clearance class
For a replacement or troubleshooting application, photographs of:rails
carriages
machine base
reference shoulders
mounting pattern
can also help identify the correct alignment approach.
Review additional engineering information on the Linear Automation USA Resources page or contact Linear Automation USA for application assistance.
Recommended Reading
How to Install Linear Guide Rails Correctly
Learn how mounting-surface preparation, master-rail installation, secondary-rail alignment, bolt tightening, carriage installation, and final inspection work together.
How Machine Rigidity Affects Linear Guide Performance
Learn why the base, rails, carriages, table, and mounting geometry must function as a complete structural system.
How Far Apart Should Linear Guide Rails Be?
Learn how transverse rail spacing influences support footprint, moment reactions, rigidity, and machine geometry.
How Far Apart Should Linear Guide Blocks Be?
Learn how longitudinal block spacing affects pitch and yaw moment reactions and guide-system rigidity.
How Mounting Orientation Affects Linear Guide Selection
Understand how horizontal, vertical, wall-mounted, inverted, and inclined guide orientations change application requirements.
Linear Guide Selection Checklist: What to Know Before Requesting a Quote
Learn what rail geometry, loads, travel, accuracy, mounting orientation, and machine information should be documented before selecting a guide system.
Sources & Technical References
THK — Mounting Procedure for LM Guides
THK documents multiple methods for installing a subsidiary rail parallel to a correctly mounted master rail, including straightedge and dial-gauge alignment, using the table as a reference, allowing the secondary rail to follow the master, and using an alignment jig.
THK — LM Guide Assembly Technical Data
THK's assembly documentation explains master-rail seating and fastening and describes using a straightedge and dial gauge to establish subsidiary-rail parallelism.
THK — Marking on the Master LM Guide and Combined Use
THK explains identification of the master rail, rail and block reference surfaces, matched serial-number use, and orientation of jointed rail systems.
THK — Procedure for Assembling Model JR
THK describes aligning parallel rails by fixing one rail first and using a dial gauge to check the side and top faces of the second rail, allowing both parallelism and level to be adjusted during mounting.
Schaeffler — Precision Rail Guides
Schaeffler's precision rail guide documentation emphasizes controlled fitting sequences, paired-rail installation, clamping against reference support surfaces, and checking rail parallelism during installation.
Linear Automation USA — Resources
Linear Automation USA provides engineering resources for profile rail selection, cut-to-length rail planning, and linear-motion applications.
Linear Automation USA
Linear Automation USA supplies industrial profile rail systems, carriages, custom-cut rails, and replacement support for linear-motion applications.